What is Yui Landslide Project?

What is Yui Landslide Project?

Protecting Lives from Disasters

Disaster Prevention Projects

Landslides are caused by a combination of various factors (topography, geology, geological structures, groundwater, etc.), so there are a wide variety of landslides measures.

These can be divided into control work and restraining work, and these two measures are combined to achieve more effectiveness.




At Yui Landslide Countermeasures projects, we are installing control works such as catchment wells, lateral borings, drainage tunnels to reduce groundwater level, and control works such as maintenance of Caisson piles to directly stop the movement of landslides.


Catchment Wells

23 catchment wells (length between 17 and 61m, diameter of 3.5m) have been constructed and maintained for the purpose of removing deep groundwater.

集水井排水状況

【Drainage in water catchment wells】
完成した集水井(地上部)

【Completed Water Catchment Well (Above Ground)】
完成した集水井(内部)

【Completed Water Catchment Well (Inside)】


21 horizontal borings (about 80m in length) have been drilled and maintained for the purpose of removing groundwater.

完成した横ボーリング

【Completed Lateral Boring (with consideration of surrounding landscape)】
完成した横ボーリング

【Completed Lateral Boring】
横ボーリング排水状況

【Drainage from Lateral Boring】
横ボーリング削孔状況</rb><rp>(</rp><rt>

【Drilling of Lateral Boring】


Caisson Piles Works

Yui is building and maintaining 61 Caisson piles (length between 37m and 88m, diameters of 5.0m and 6.5m) to directly stop the movement of landslides by using the resistance of the piles.



【Caisson Piles under Construction】




Drainage Tunnels

Drainage tunnels (Yamanaka Drainage Tunnel, length of 768m, and Okubo Drainage Tunnel, length of 712m) are being constructed in the bedrock to remove groundwater deep in the ground using pipes attached to the tunnels.

①トンネル掘削(ローターヘッド)

【①Tunnel Excavation (Rotor Head)】
施工機械。左より、吹付機、穿孔機、掘削機(施工は掘削→吹付け→ロックボルト)

【Construction Equipment. From left: shotcreting machine, boring machine, cutting machine (Construction Process: Excavation→Spraying→Rock Bolt)】
②モルタル吹き付け

【②Mortar Spraying】
③ロックボルト

【③Lock Bolt】
④トンネル内部(広い箇所は集水室)

【④Inside of the Tunnel (The large area is the water collection room)】


The next page explains the effectiveness of the projects.